Market Brief
GYGO Global GPU Infrastructure Brief
Published
Coverage: November 9–15, 2026
This week: Revalidate delivery commitments and counterparties. Texas permitting disclosures and TELUS’s Vancouver withdrawal could affect existing shortlists. A newly opened Brazilian facility offers a plausible smaller-block lead, while most international expansion announcements remain future capacity. Client implications are brokerage assessments, not provider commitments.
1. Texas: permitting risk and a change in Fermi’s prospective tenants
- What changed: Net Power’s November 12 quarterly filing says TCEQ restored electronic submissions for certain general permits on November 9, but applications require review and no longer receive automatic approval or provisional coverage. The filing explicitly says this does not lift the data-center permitting pause. Its prospective customer may defer or choose another state if permits miss its timeline. This is a developer’s regulatory disclosure, not a new statewide prohibition. Net Power filing, November 12, 2026
- Tenant update: Fermi terminated its TensorWave lease and associated AMD credit support. An undisclosed hyperscaler signed development agreements for 600 MW of power capacity beginning in 2027, including a US$200 million prepayment agreement and US$15 million early-construction agreement. The long-term lease remains unfinished. These sums are development commitments, not customer rent. Fermi release, November 12, 2026
- Client implication: For Texas projects requiring new permits, including dedicated generation, obtain written permit status before accepting an energization date. Do not carry forward Fermi’s former tenant commitment or describe the proposed 600 MW as energized, leased inventory.
2. TELUS exits two planned Vancouver facilities | Canada
- What changed: November 14 reporting citing confirmation from both companies says TELUS withdrew from Westbank’s M3/Mount Pleasant and 150 West Georgia projects. Westbank intends to continue with an unnamed replacement partner. M3’s original schedule called for opening at end-2026 and scaling through 2028; West Georgia was planned for 2029. The previously announced 85 MW initial power allocation covered the broader network, not confirmed available capacity at either building. DataCentre.ca, November 14, 2026
- Client implication: Requalify proposals tied to these projects, particularly Q1 2027 requirements. Ask who will contract, operate and be accountable for delivery. The withdrawal does not confirm both projects are cancelled, but original provider and schedule assumptions need revalidation.
3. CoreWeave reports more active power and financing for shorter contracts
- What changed: CoreWeave’s November 10 disclosure reports more than 200 MW of active power added during Q3, reaching over 1.7 GW, versus over 4.6 GW contracted power. International contracted power exceeds 1.3 GW, including India, Indonesia and Spain. It also closed a US$2.6 billion financing facility designed to support shorter-duration customer contracts. CoreWeave results, November 10, 2026
- Client implication: Ask whether shorter GPU-cloud commitments are available for clients unwilling to lock in a multiyear deployment. Financing creates a commercial opening, not a published offer. Active power does not establish unallocated GPUs. Obtain the region, GPU model, start date and reserved capacity. No customer pricing was disclosed.
4. Astella opens approximately 3.5 MW in Curitiba | Brazil
- What changed: TI Inside reports that Grupo ABL’s Astella began operating on November 11 with approximately 3.5 MW, expandable toward 5 MW subject to occupancy, additional power contracting and equipment installation. The report describes liquid cooling and high-density racks alongside colocation and cloud services. TI Inside, November 11, 2026
- Client implication: A plausible lead for 1–5 MW requirements, especially Brazilian-resident workloads. Unleased capacity, IT-versus-facility MW, rack limits and acceptance of specific B300/GB300 systems remain unverified. Opening does not mean all 3.5 MW is available to a new tenant. No BRL or USD customer quote was published; sovereignty positioning does not establish regulatory certification.
5. Querétaro faces a new legal challenge | Mexico
- What changed: Actions announced November 9 and reported November 10 include an amparo challenge by Voceras de la Madre Tierra and efforts to change the environmental code concerning data centers, water and electricity impacts. The group also requested a provisional suspension of new installations. Meganoticias, November 10, 2026
- Client implication: Add project-specific litigation and environmental-permit checks to Querétaro proposals. A requested suspension is not a granted injunction or enacted moratorium; the reviewed report establishes neither. No provider-specific MW was shown to be blocked. No fresh, provider-backed release of available GPU-ready capacity in Mexico was verified this week.
6. Colt advances Berlin’s substation; buildings remain in planning | Germany
- What changed: November 10 reporting confirms work on the 110 kV substation for Berlin 1 and 2. Colt clarified that construction of the data-center buildings has not started. The campus targets 54 MW IT, with Berlin 1 expected by end-2028. DCD, November 10, 2026
- Power status: Colt reports an 80 MVA power contract for the combined 54 MW IT campus. Contracted supply and substation works do not establish an energized building. Colt project specification, reviewed November 16, 2026
- Client implication: Relevant to 10+ MW planning from 2028 onward. Obtain phase-specific delivery commitments and GPU-cooling specifications. No EUR-denominated rent was disclosed.
7. SoftBank, Grab and PETROS advance Malaysian development agreements
- What changed: November 9 joint development agreements contemplate US$1.85 billion in initial seed capital across Sarawak and Peninsular Malaysia. This is development capital, not rent. SoftBank announcement, November 9, 2026
- Capacity status: Sarawak accounts for US$1 billion, approximately MYR4.07 billion, and a long-term 5 GW compute ambition. Investment is staged against development, customer-contract and closing milestones. SoftBank/PETROS announcement, November 9, 2026
- Client implication: A consequential future sourcing channel for large Southeast Asian deployments, but not a near-term capacity alternative. No phase-level delivery date, available MW or customer pricing was disclosed.
Regional watch
Middle East watch: Syntys broke ground on a 20 MW Qatar facility on November 12 on an existing campus. Reporting identifies an AI/HPC focus, but no commissioning date or customer commitments. Keep it on the future pipeline rather than a dated deployment shortlist. Property News International, November 13, 2026
Africa: No comparably material, sufficiently verified new African capacity milestone made this week’s ranking.
Brokerage follow-ups
- Recheck active proposals: Texas permit dependencies; Vancouver contracting entity and revised schedule; any reliance on Fermi’s former TensorWave agreement.
- Qualify the new lead: ask Astella for uncommitted IT MW, contiguous space, utility service evidence and cooling acceptance for the client’s exact H100/H200/B300/GB300 configuration.
- Test commercial flexibility: request CoreWeave options by GPU model, region, term, prepayment and minimum commitment.
- Normalize pricing: no comparable new all-in colo quote was verified this week. Require currency and per-kW/month basis, separating base rent, electricity, PUE, cooling, taxes, installation costs and escalators.
- For cross-border choices: confirm permitted data locations, backup locations and remote administrative access before comparing international sites solely on cost.